> Others are predictable, but take a long time to start and stop - gas, coal(several hours), nuclear(1 day to start, fast to stop, but very expensive).
The start time is long but that does not say much about the overall operations.
> Modern nuclear plants with light water reactors are designed to have maneuvering capabilities in the 30-100% range with 5%/minute slope, up to 140 MW/minute
> In France, with an average of 2 reactors out of 3 available for load variations, the overall power adjustment capacity of the nuclear fleet equates to 21,000 MW (i.e. equivalent to the output of 21 reactors) in less than 30 minutes.
The variability of France’s nuclear fleet is harder on the generator (valves and structures susceptible to thermal stresses in particular), and a possible contributor to their inability to keep their fleet in good repair.
Arguably, if cost effective, nuclear is best run at full output as consistently as possible, with other systems buffering that supply with demand (hydro storage, batteries, demand response, etc).
The start time is long but that does not say much about the overall operations.
> Modern nuclear plants with light water reactors are designed to have maneuvering capabilities in the 30-100% range with 5%/minute slope, up to 140 MW/minute
https://en.wikipedia.org/wiki/Load-following_power_plant
and https://thundersaidenergy.com/downloads/power-plants-cold-st...
> In France, with an average of 2 reactors out of 3 available for load variations, the overall power adjustment capacity of the nuclear fleet equates to 21,000 MW (i.e. equivalent to the output of 21 reactors) in less than 30 minutes.
https://www.powermag.com/flexible-operation-of-nuclear-power...