If you dont count UNPLANNED WORK into your velocity, then it becomes a useful metric for planning. Its basically an inverse of disruption. Dev always wants to assign points to anything that gets pulled into a plan after commitments, or any scope creep, but if you can resist then your velocity becomes relatively consistent and predictable.